JAN. 28, 2098 – WAYLAND, MA – Post - M2M By the Numbers - It All Adds Up!
JAN. 22, 2098 – WAVELAND, MS – Day 99 - House assignments revealed! Families, builders, W2W gather for ceremony.!
JAN. 18, 2008 – WAVELAND, MS – Day 95 - Wrapping Up... press conference scheduled to announce who is getting which house!
JAN. 11, 2008 – WAVELAND, MS – Day 88 - Another Cindy Update!
JAN. 10, 2008 – WAVELAND, MS – Day 87 - More than 50 on sites–flooring, painting and swing assembly!!
JAN. 8, 2008 – WAVELAND, MS – Day 85 - BC Rules - in Landscaping, for sure!!
JAN. 2, 2008 – WAVELAND, MS – Day 79 - Kicking off the new year in high gear!
DEC. 26, 2007 – WAVELAND, MS – Day 65 - Update on activity during the holiday week.
DEC. 13, 2007 – WAVELAND, MS – Day 59 - Medfield connects with future homeowner via video and cell phone during busy work day.
DEC. 12, 2007 – WAVELAND, MS – Day 58 - Cabinets going in all around! Architect Michael Collins and son visit.
DEC. 11, 2007 – WAVELAND, MS – Day 57 - Week 9 starts; painters finished our 8 homes and more; interior finish work starts with a jump.
NOV. 30, 2007 – WAVELAND, MS – Day 46 - Drywallers wrap up work; preparing for the next week.
NOV. 29, 2007 – WAVELAND, MS – Day 45 - Drywallers working quickly, move to Taranto and Maple Streets.
NOV. 28, 2007 – WAVELAND, MS – Day 44 - Drywallers get started... three teams working.
THANKSGIVING BREAK – SITE CLOSED from Nov. 20-27.
NOV. 13, 2007 – WAVELAND, MS – Day 29 - New worker crews arriving including electricians and plumbers.
NOV. 12, 2007 – WAVELAND, MS – Day 28 - Week four wraps, carpenters get high praise from local building inspector.
NOV. 9, 2007 – WAVELAND, MS – Day 25 - Decks on at Maple and Taranto. Families visit sites to help with cleanup.
NOV. 7, 2007 – WAVELAND, MS – Day 23 - Wrapping up week 3.
NOV. 1, 2007 – WAVELAND, MS – Day 17 - More progress at Combel.
OCT. 31, 2007 – WAVELAND, MS – Day 16 - Week 3 begins
OCT. 29, 2007 – WAVELAND, MS – Day 14 - Week 2 comes to an end... roofers and exterior trim teams are coming down for week 3. Read Cindy's report. ALSO: back home in Wayland, W2W taped a half-hour TV "special" for WAYCAM (Ch. 9) today which will air on Sat. Nov. 3rd at 1 and 7 pm! Watch it!!!!!
OCT. 27, 2007 – WAVELAND, MS – Day 12 - Photos by volunteer Myra Snyder.
OCT. 26, 2007 – WAVELAND, MS – Day 11 - Productive day by Quality Framing crew, visit by Destiny and Tristan.
OCT. 25, 2007 – WAVELAND, MS – Day 10 - Day 1 of Week 2 (we gotta stop this numbering) was a fast start in cool, dryweather with a new framing crew.
OCT. 24, 2007 – WAVELAND, MS – Day 9 - Wrap up on Week 1 and news regards the start of week 2 in Waveland
OCT. 22, 2007 – WAVELAND, MS – Day 7 - Report on Week 1 Progress – four houses framed plus windows and doors; upcoming projects; families participate.
OCT. 20, 2007 – WAVELAND, MS – Day 5 - Great progress as all four houses on Combel are framed, some have windows installed, interior walls set. "Rebuilding Together" crew starting to arrive, some will work on Ms. Hazel's house (last fall's project) installing flooring.
OCT. 19, 2007 – WAVELAND, MS – Day 4 - The weather cleared on Friday and huge progress was made; update on families.
OCT. 18, 2007 – WAVELAND, MS – Day 3 - Severe weather interrupts work; one of the home recipients visits; update on interview with candidate.
OCT. 17, 2007 – WAVELAND, MS – Day 2 - Framing nearly done at Combel
OCT. 16, 2007 – WAVELAND, MS – Day 1 - Start of work sees platforms set on foundation piers.